Installation of Aermec Chiller Units
Recently using a liebherr LTM 1100/2 MRI completed yet another successful Contract Lift at a major Data Centre in Slough installing 2no Aermec Chiller Units weighing in at 15 tonnes each from the sites compound area to the Chiller compound at roof level.
Each Chiller Unit was a 16 point lift so providing and using the correct certified equipment was vital. We used our own 4.0m x 1.7msteel crane mats to reduce the outrigger loadings to achieve the required Ground Bearing Pressure. This was one of many Contract Lifts to be completed at this project, we still have 6 more lifts to complete using the 200te, 250te, 300te, 450te, & 500te Cranes. Bring it on 💪🏻